DCP Key generation must be handled as follows:
Pre-Release Single Screenings
- Maximum 7.5 hours KDM activation window, from start to finish.
- Targeting a single playback server.
Multi-Site EARLY Previews
(with screenings that end earlier than 00.01 on the release date)
- Key Activation: 8 AM on the morning of the Previews date.
- Key Deactivation: 8 AM on the morning after the Previews date.
Multi-Site Previews
(with screenings beginning earlier than 00:01 on the release date and playing through opening)
- Key Activation: 8 AM on the morning of the Previews date.
- Key Deactivation: Follow standard territory protocol.
General Release
(with screenings beginning 00:01 or later on the release date)
- Key Activation: 8 AM on the morning prior to the release date.
Comments